January 10th PROD Cluster Upgrade (2 of 4)
Scheduled Maintenance Report for Synapse
Completed
The scheduled maintenance has been completed.
Posted Jan 10, 2024 - 02:42 PST
Verifying
Verification is currently underway for the maintenance items.
Posted Jan 10, 2024 - 02:34 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 10, 2024 - 01:00 PST
Scheduled
We continue to make enhancements to the Infrastructure for our customers. We are performing the second of four planned Cluster updates to our PROD environment on Wednesday, January 10th between 1am and 4am PST. During the maintenance, we will be closely monitoring to prevent & minimize interruption to services and transactions. We will notify here when the maintenance has started and completed.
Posted Jan 02, 2024 - 21:41 PST
This scheduled maintenance affected: CORE APIs.